Transportation Bond Projects

 

Transportation Bond Projects

 Apex Transportation Bond Projects Map (Adobe PDF)

The 2004 transportation bond referendum resulted in the completion of 2.2 miles of the two lane outer loop of Apex Peakway, 1.1 miles of sidewalk extensions, and upgrades to two major intersections.  Additionally, federal surface transportation matching grant funds will result in the completion of one additional major intersection upgrade and an additional 1.1 miles of sidewalk extensions during 2012.

Phase I Projects, 2005-2008

ID

Description

Final Construction Cost

Status

 

 

 

 

AP 1

Apex Peakway:  Hillcrest Road to N. Salem Street

$985,000

Completed 2008

 

 

 

 

AP 5, AP 6, AP 8

Apex Peakway:  S. Salem Street to Olive Chapel Road

$3,321,000

Completed 2008

 

 

 

 

IU 2

Salem Street and NC 55 – Intersection Upgrade

$330,000

Completed 2008

 

 

 

 

IU 3

Lake Pine Drive and US 64 – Intersection Upgrade

$247,000

Completed 2008

 

 

 

 

SW 1

Laura Duncan Road Sidewalk

$142,000

Completed 2008

 

 

 

 

SW 2

Olive Chapel Road Sidewalk

$179,000

Completed 2004 - 2008

 

 

 

 

TOTAL COST OF PHASE I

$5,204,000

 


Phase II Projects, 2009-2012

ID

Description

Final Construction Cost

Status

 

 

 

 

AP 2

Apex Peakway:  Tingen Road

$129,350

Completed 2009

 

 

 

 

AP 3

Apex Peakway:  N. Salem Street to New Dover Road

$6,000,000

Completed 2011

 

 

 

 

IU 5

Signalization along the Apex Peakway & NC 55

 

$100,000

Completed 2005 - 2010

 

 

 

 

TOTAL COST OF PHASE II

$6,229,350

 

 

Transportation Bond Projects Funded by Surface Transportation Program – Direct Allocation

The following projects were originally identified as priorities in the 2004 Bond Referendum.  These projects are now being funded through a matching grant program by the Federal Highway Administration.

ID

Description

Final Construction Cost

Status

 

 

 

 

SW 4

Old Raleigh Road Sidewalk

This project will fill in gaps along Old Raleigh Road and provide a continuous route from the Town Campus to Eva Perry Library.  An approximate 3,400 feet of sidewalk is required.  This project is being funded by a Federal grant as part of the American Recovery and Reinvestment Act of 2009.

$380,000

Construction in 2012

 

 

 

 

IU 1

Realign Lufkin Road at Ten-Ten Road

This proximity to the US 1 Bridge and the US 1 On/Off Ramp makes the current intersection difficult and unsafe to maneuver, especially at peak hour traffic intervals.  This project will realign Lufkin Road to tie in to Ten-Ten Road directly opposite the US 1 On/Off Ramp.  A traffic signal will be installed at the new intersection of Lufkin Road and Ten-Ten Road.

$2,000,000

Construction in 2012

 

 

 

 

SW 3

Center Street Sidewalk

This project will fill in gaps between the neighborhoods along Center Street and the Downtown area.  An approximate 2,600 feet of sidewalk is required.

$370,000

Construction in 2012

 

 

 

 

 

 

 

 

TOTAL COST OF TRANSPORTATION BOND PROJECTS FUNDED BY SURFACE TRANSPORTATION PROGRAM – DIRECT ALLOCATION

$2,750,000

 

Future Construction

ID

Description

Estimated Cost

 

 

 

 

 

AP 7

Apex Peakway:  Schieffelin Road Connector

Construct the Apex Peakway from NC 55 to Schieffelin Road, approximately 1,600 feet.

$2,000,000

Future Construction

 

 

 

 

AP 9

Apex Peakway:  S. Salem Interchange

$4,000,000

Future Construction

 

 

 

 

TOTAL COST OF FUTURE CONSTRUCTION

$6,000,000