Engineering Services Apex Peakway Construction
The Apex Peakway between N. Salem Street and Laura Duncan Road is currently under construction. Please check back periodically for schedule updates and construction photos.
Peakway Schedule – N. Salem Street to Laura Duncan Road
May 2010 – Jul. 2010: Contract awarded, mobilization of equipment, clearing and grubbing, erosion control devices, and utility bores.
Jun. 2010 – Aug. 2010: Work east of bridge. Culverts being installed and grading work, erosion control maintenance.
Aug. 2010 – Nov. 2010: Bridge construction. Bridge piers drilled, column construction. erosion control maintenance
Nov. 2010 – Mar. 2011 Bridge construction. Concrete deck poured, bridge approach slabs, sidewalk and railing erosion control maintenance.
Nov. 2010 – Feb. 2011: Work west of bridge. Water, sewer, and storm drain installation; grading erosion control maintenance.
Dec. 2010 – Feb. 2011: Work east of bridge. Sidewalk installation, paving, seeding, and pavement marking, erosion control maintenance.
Feb. 2011 – Apr. 2011: Work west of bridge. Curb and gutter installation, sidewalk, paving, seeding, and pavement marking erosion control maintenance
Jun. 2011 – Jul. 2011: Final punchlist and walkthrough. Peakway open.